| 16R Glidepath | | Construction of Runway 16R Glide path equipment building. | |
| A380 Apron Works Bay 61, 63 | | Excavation, Demolition Sheet piling and Slurry Backfilling of Fuel Lines. | |
| A380 Project | View Gallery | This project was undertaken with the introduction of the Airbus A380 to Sydney Airport. When compared to existing passenger aircraft, the A380 is larger in height, length, wingspan, weight & passenger capacity.
To accommodate the A380 aircraft, Sydney Airport Corporation Limited (SACL) and JUHI, an incorporated joint venture between BP, Caltex, Mobil, Qantas & Shell, require the modification of Aviation Hydrant Systems at up to 10 Parking Bays to commence 2006 to 2008 | | Location: Sydney Airport | | Duration: 24 Months | | Cost: $4,000,000 |
|
| Aircraft Waste Dump-Civil Works | | Bulk excavation, sheetpile shoring installation & removal, dewatering and asphalt. | |
| Airds - Fonthill & Greengate Precinct Campbelltown Stormwater Drainage, Road Works & Water Reticulation | | Upgrade of existing road and domestic housing stormwater drainage system. Demolition of existing asphalt paving & road base, kerb & gutter, footpaths, stormwater pits and drainage pipes lines. Reconstruction of new road sub-base and base course, lay new asphalt wearing course. Construction of new stormwater pipework & pits from existing housing to connect with street drainage. Construction of new kerb &gutters and footpaths. Upgrade and extension of current potable water reticulation system and sewerage system. | | Location: Airds - Fonthill & Greengate Precinct Campbelltown | | Duration: Mar 2011 - Aug 2011 | | Cost: $803,157 |
|
| Bay 24 A380 Apron Pavement Works | | Remove and reinstatement of flexural concrete aircraft apron. | |
| Bay 55 A380 Apron Pavement Works | | Remove and reinstatement of flexural concrete aircraft apron. | |
| Bay 73 Apron Pavement Works | | Construction of new flexural concrete aircraft apron. | |
| Berala/Carramar Tennis & Rectin Club | | Excavation, Kerb & Gutter Works, Stormwater Drainage, Construction of asphalt pavement. | |
| Campbell Hill Pioneer Reserve | | Construct new access road, concrete weir, Sediment basin & Trash rack. | |
| Canterbury Council Earlwood Bardwell Park Bowling Club Carpark & Drainage | | Construction of new carpark, stormwater drainage pits and detention system, concrete footpaths, kerb & gutter, landscaping and fencing works. | |
| Canterbury Council Oswald Street Campsie - Stormwater Rehabilitation Works | | Construction of new length of 1200mm diameter stormwater pipe on new alignment across Oswald Street to improve stormwater flow between existing pits. | |
| Charles St & Parkes St | View Gallery | Construct a new 4 lane carriageway, Concrete Retaining walls, stormwater drainage, earthworks.
Citywide Civil Engineering was engaged by Parramatta City Council for this important part of road infrastructure due to the complicated conditions that exist as a result of the location of the site.
The project involved clearing & demolitions, bulk excavation, concrete retaining walls & architectural noise walls, pedestrian fencing, screw pile & beam construction for new footway, kerb & gutter, stormwater drainage, slip lane construction, new road pavements, traffic loops, line marking & major traffic control & management.
| | Location: Parramatta | | Duration: 6 Months | | Cost: $1,500,000 |
|
| Contractors Compound Services | | Reticulation of Sewer, Water, Electrical and Comm.\'s to contractors compound. | |
| Contractors Compound Services | | Reticulation of Sewer, Water, Electrical and Comms to contractors compound. | | Location: Sydney Airport South East Sector | | Duration: Oct 2004 - Dec 2004 | | Cost: $330,000 |
|
| Domestic Multi Story Carpark | | Construction of new vehicle entry/exit driveways, Relocation of Car wash area. | |
| Domestic Precinct Public and Economy Hire Car Pick-up Relocation | | The existing Economy Hire Car Pick Up is to be relocated between Fourth and Fifth Streets with own dedicated access controlled entry/exit point. The primary purpose is to provide a minimum 19 undercover pickup spaces. The existing T2 Arrivals Pick-up Area is to be relocated between Fourth and Fifth Streets with access controlled entry/exit point and free entry for a limited time. The primary purpose is to increase the Public Pick up capacity and reduce traffic congestion within the Domestic Precinct by constructing a minimum of 53 car spaces including 16 undercover car parking spaces, two undercover public waiting areas and covered walkway. The existing T2 Arrivals Pick-up Area is to be changed to premium limousine area with an access controlled entry point. | |
| Endeavour Energy Rehabilition of Southern Carpark Huntingwood | | The demolition and removal of existing asphalt paved carpark including subgrade poles and conduits. Complete reconstruction of carpark from preparation and re-compaction of new sub-grade course, sub-base, base course and asphalt wearing course, and including construction of new stormwater drainage system, kerb & gutter & lighting poles and electrical works. | | Location: Endeavour Energy Office Complex Huntingwood | | Duration: Sep 2011 - Apr 2012 | | Cost: $1,338,378 |
|
| Gate 25–Sec Access Syd Intel Term | | Flexible pavement, Chainwire fencing, Supply & Install new automatic swing gate. | |
| Gate 31 & 32 – Aerobridge Upgrade | | Demolish existing pavement, construct new Aerobridge footings and raised Bondek concrete slab. | |
| GBAS | | Construct of Piled Footings, Slabs & Shed Installation. | |
| Helipad | | Construction of Helipad and perimeter road. | |
| Hydrant Modifications S.I.T Bay 22 | | Removal and replacement of concrete aircraft apron. | |
| Island 39 Regrading Works | | Removal of CLER and Fire station Foundations. | |
| James Ruse Drive | | Extension of right hand turning lane. | |
| JUHI Bay 10, 5, 9, 4, Shell Works | | Excavation, Demolition Sheet piling and Slurry Backfilling of Fuel Lines. | |
| JUHI Bay 24 Shell Works | | Excavation, Demolition, Sheet piling and Slurry Backfilling of Fuel Lines. | |
| JUHI Bay 55 Shell Works | | Excavation, Demolition and Slurry Backfilling of Fuel Lines. | |
| JUHI Bay 57 Shell Works | | Citywide Civil undertook a project for Sydney Airports Corporation at Sydney Airport International terminal between November and December 2006 where we were involved in excavation, demolition and slurry backfilling of fuel lines of Bay 57. | |
| JUHI Road Pavement Repairs | | Demolition & Repair of Pavement. | |
| JUHI Shell Aviation Mascot Sydney Airport Tank 5 Early Works Contract | | Early works Contract for Tank 5 Remedial Works comprising set up site compound, removal of existing concrete bund wall for access removal of pebble protection and part of HDPE bund liner, protection existing pipework and electrical services. | | Location: Sydney Airport JUHI Shell Aviation Facility Link Road Mascot | | Duration: Aug 2011 - Dec 2011 | | Cost: $123,917 |
|
| JUHI Shell Aviation Tank 5 Foundation Reconstruction and Civil Works | | The demolition and removal of existing concrete storage tank foundations and associated minor foundations. Preparation of base course and installation and rolling of new subgrade. Construction of new tank concrete ring beam foundation and laying and compaction of internal fill to ring beam. | | Location: Sydney Airport JUHI Shell Aviation Facility | | Duration: Aug 2011 - Dec 2011 | | Cost: $507,179 |
|
| JUHI Tank 4 Foundation Reconstruction | | The demolition and removal of existing concrete storage tank foundations and associated minor foundations. Preparation of base course and installation and rolling of new subgrade. Construction of new tank foundations. | | Location: Sydney Airport JUHI Shell Avaiation Facility Link Road Mascot | | Duration: Dec 2009 - Mar 2010 | | Cost: $195,000 |
|
| Liverpool Golf Club Hollywood Drive | | Stormwater Drainage, K & Gr, Earthworks, Subbase. Asphalt pavement. | |
| Mitchel Road Drainage | | Stormwater Drainage including installation of Atlantis Cells and minor roadworks. | |
| Moss Vale Road, Bomaderry | | Construction of additional turning lane. | |
| NLA Runway Cabling (Pit & Duct) | | Trenching, Reticulation of Electrical Pits & Ducts for NLA taxiways. | |
| NLA Shoulder Pavements Trial | | Demolition of Pavements, Protection of Ex. Services, Construction to Airside Road. | |
| Perimeter Lighting | | Trenching, Reticulation of Electrical Cabling, Lighting, Pits & Ducts. | |
| Pier B Cutback Plinth | | Extension of existing concrete plinth. | |
| Qantas A380 Hard Stand | | Construction of Piles and hardstand for A380 Northern pond. | |
| Qantas Tug Refuelling Facility Demolition | | Demo of fuel and tanks and removal of contaminated material. | |
| Quantas Tug Refuelling Facility Reinstatement | | Pavement Reinstatement of redundant TUG Refueling Facility | | Location: Sydney Airport International Terminal | | Duration: Mar 2008 - May 2008 | | Cost: $900,000 |
|
| Racetrack Conveyors at Terminal T2 | | Concrete plinth demolition and replacement. Asphalt reinstatement. | |
| Realignment of Ross Smith Avenue | View Gallery | Works comprise of a re-aligned section of Ross Smith Avenue and associated road works on Arthur Butler Road due to this section of road being a major "black spot" for the likelihood of accidents.
The various elements of the works included demolition, pavement works, line marking, reticulation of stormwater, electrical and communications services, road signage, street lighting, grass restoration, turfing and the construction of a flood protection earth bund wall. | | Location: Ross Smith Avenue | | Duration: 3 Months | | Cost: $600,000 |
|
| Residential Development & New Road Construction | | Bulk & detailed excavation works for underground carpark and building foundations for four multistorey residential blocks. Excavation for stormwater drainage and on-site detention tank Construction of new internal access road including kerb & gutter and asphalt works. | | Location: 162 - 182 Woodland Street Balgowlah | | Duration: Aug 2010 - May 2012 | | Cost: $614,309 |
|
| Rocky Point Road | View Gallery | This project was undertaken due to local flooding problems in the main shopping district of Ramsgate. Due to numerous complaints from shop operators & local residents Kogarah Council undertook the work to alleviate the problem.
The Contract was awarded to Citywide Civil Engineering due to the location of the works being on one of Southern Sydney's main arterial roads. As a result the work had to be carried out in limited working hours in which the worksite had to be opened to traffic at the completion of each shift using steel plates. | | Location: Rocky Point Road Ramsgate | | Duration: 2 Months | | Cost: $150,000 |
|
| RTA Rehabilitation of Box Culverts on Henry Lawson Drive East Hills | | The removal of existing corroded precast reinforced concrete box culverts and the installation of six new precast crown units which involves the installation of upstream and downstream coffer dams to allow the works to be undertake in the dry. | |
| Runway & Taziway AGL Early Work Trench Repairs | | This project was part of Sydney Airport\'s taxiway lighting respacing project. CCE\'s work included surface repairs to a narrow trench which contains conduits for future airfield ground lighting. A trench had to be profiled 470mm wide to a depth of 50mm This trench is then re-sheeted with BC14 asphalt mix. This work also includes and airfield lighting component. This work comprises of the removal and reinstatement of shallow base cans, repairs to secondary sables and a small number of deep base canisters. | | Location: Sydney Airport - International Terminal | | Duration: Jul 2009 - Sep 2009 | | Cost: $672,438 |
|
| Runway 25 - RESA | | Construction of the pavements of the Airport runway surface and RESA surface. | |
| Runway 25 - RESA Deck Slabs, Fender Walls & Cross Beams | | Part of the RESA is to be supported on a series of land bridge structures that are required to span over the existing Southern and Western Suburbs Ocean Outfall Sewer (SWSOOS), the M5 East Tunnel, and the airport perimiter road which is to be realigned as part of these works. The land bridge structures are constructed of precast planks supported on the headstocks, and CFA and bored piles.
| |
| Runway Ends Compliance Works (RESA) | | Excavation, construction of pavement, turfing and asphalt. | |
| Sutherland Shire Council | | Road construction and associated works. | |
| Sutherland Shire Council Off Road Shared Cycleway Oakwood & Waratah Streets | | Construction of shared pedestrian and cycleways along Oakwood, Waratah & Leonay Streets comprising new footpaths, road crossings, drainage works and new tree planting. | |
| Sutherland Shire Council Roundabout | | Construction of a new roundabout with associated splitter islands new kerb & gutter with associated grated gully inlets, new pram ramps and footpathsand asphalt re-sheet of the intersection of Sylvania Road and Garnet Road | | Location: Intersection of Sylvania & Garnet Roads Miranda | | Duration: Feb 2012 | | Cost: $149,203 |
|
| SW Sector Early Works | | Demolition of Struct, Pavement Works to Airside Road & Fire Access, Fencing & Hydromulching. | |
| Sydney International - ALPHA 5 | | New Generation Aircraft Fillets. | |
| T1 High Mast Flood lighting | | Erection of Floodlight, Construct of Footings, Electrical Pit & Duct Works. | |
| T1 Pier C | | Demolition of existing plinths and carousels and construct new laterals. | |
| T1 Pier C (Stage 5) | | Demolition of existing plinths and carousels and construct new laterals. | |
| T1 T2 Floodlighting | View Gallery | This project was undertaken due to the existing floodlights and associated electrical works at Sydney Airport were designed & installed at various times over the last 20 years for the type of aircraft operating at the time.
The general illumination on some Terminal parking bays was below that required by the Civil Aviation Safety Authority\'s Manual of Standards (MOS) for the type of large bodied aircraft now using the bays. | | Location: Sydney Airport | | Cost: $2,500,000 |
|
| T2 Domestic Terminal Trans Mod | | Demolition of Pavements, Kerb and Gutter, Stainless Steel Corral Construction. | |
| T2 Retail Redevelopment | | Construct Concrete Footings and reconstruction rigid & flexible pavements. | |
| T2 Term Gates 32-34 Retail Development | | Construct of rigid & flexible aircraft pavements, Stormwater struct, light pole & aerobridge footings. | |
| T2 Terminal Pier A&B -Syd Dom Term | | Erection of Floodlight, Construct of Footings, Electrical Pit & Duct Works. | |
| T2 Toilet Block External Works | View Gallery | | Excavation, Footings, Steelwork, Suspended Slab, Cladding Construction. | | Location: T2 Pier A | | Duration: 3 months | | Cost: $300,000 |
|
| Taxiway Bravo & Charlie | | Rehabilitation of both Taxiways Bravo and Charlie and Drainage Works. | |
| Test Rolling of Runway Flanks | | Test rolling of runway flanks. | |
| Tilt Tray Baggage Sorter Platforms | | Steel Fabrication & Installation of Steel Platforms to Baggage Sorter T1. | |
| Upgrade of 11kV Cable | | Excavation and installation of a high voltage cable. | |
| Warcoo Ave, Gymea | | Widening and sealing of existing local road. | |
| Windsor Flood Evacuation | | Earthworks, Drainage Works, Roadworks and level Crossing construction. | |
| Grindleys Qantas Gate 12 Reconfiguration & Refurbishment | | Demolition and removal of existing conrcrete apron. Excavation for and construction of concrete foundations for new light towers, new building extension and new aerobridges. Reinstatement of concrete apron and slabs and associated paving works. | | Location: Sydney Airport Domestic Terminal 3 Qantas Gate 12 | | Duration: May 2012 - July 2012 | | Cost: $362,631 |
|
| JUHI Shell Aviation Domestic Terminal 2 Pier A Upgrade to Jet Fuel Hydrant Pipe Line Civil Works | | Detailed excavation for the installation of new fuel lines and hydrants for the new apron extension at Pier A, including piled sections for the installation and connection to existing pipe system. Supply & lay leanmix concrete trench infill. | | Location: Sydney Airport Terminal 2 Pier A Domestic Terminal Mascot | | Duration: Sep 2011 - June 2012 | | Cost: $919,499 |
|
| Kogarah City Council Beverly Park Golf Course Channel Diversion Stage 1 | | Reconstruction of existing storm water drainage channel with new offtake structure to allow discharge of stormwater through new culvert to stilling basin for irrigation of Golf Course. Construction works included excavation and installation of under road culvert crossing, stilling basin and final discharge structure for return of excess water to stormwater channel, associated road works and landscaping works. | | Location: Ferry Road Kogarah Sydney | | Duration: May 2012 - June 2012 | | Cost: $548,628 |
|
| Parkview Constructions Powerhouse Apartments Botany Road Rosebery | | Detailed excavation for pad & strip footings, piled foundations and lift pits for the construction of 5No apartment blocks. | | Location: 797 - 801 Botany Road Rosebery Sydney | | Duration: Sep 2011 - May 2012 | | Cost: $70,860 |
|
| Parramatta Council Epping Town Centre Stage 1 | | Demolition and removal of existing pedestrian asphalt paving, pavers and kerb and gutters. Construction of new sections of kerb and gutter, raising of existing covers to new footpath level, laying new pavers as borders to asphalt infill for new footpaths, Refurbishment of existing landscaped areas with new plantings. Supply and installation of new street furniture. | | Location: Epping Town Centre | | Duration: Feb 2012 - May 2012 | | Cost: $250,877 |
|
| Shell Aviation Reinstatement Tank 5 Bund wall and Associated Works | | Reinstatement of Tank 5 Bund Wall and pebble protection to internal bund liner, construction of new stairs foundation pads, new vehicle parking areas, trench reinstatement and fence alignment. | | Location: Sydney Airport JUHI Shell Aviation Facility | | Duration: May 2012 - June 2012 | | Cost: $170,928 |
|
|